File Number
26-775
Type
Minute Order
Status
Agenda Ready
Final Action
CC - CONSENT ITEM: (1) Approval of Revised Final Plans and Specifications for Phase 1 of the Better Overland Project, CIP No. PS029,; (2) Award of a Construction Contract to Toro Enterprises, Inc. as the Lowest Responsive and Responsible Bidder, in the Amount of $1,253,149 for Phase 1 of the Better Overland Project,; and (3) Authorization to the Public Works Director/City Engineer to Approve Change Orders to the Contract in an Amount Not-to-Exceed $288,163.03 (23%) to Cover Contingency Costs.
On Agenda
9/28/2026
In Control
City Council Meeting Agenda

Full Text

title

CC - CONSENT ITEM: (1) Approval of Revised Final Plans and Specifications for Phase 1 of the Better Overland Project, CIP No. PS029,; (2) Award of a Construction Contract to Toro Enterprises, Inc. as the Lowest Responsive and Responsible Bidder, in the Amount of $1,253,149 for Phase 1 of the Better Overland Project,; and (3) Authorization to the Public Works Director/City Engineer to Approve Change Orders to the Contract in an Amount Not-to-Exceed $288,163.03 (23%) to Cover Contingency Costs.

 

 

body

Meeting Date:                     June 22, 2026

 

Contact/Dept.:                     Thomas Check/Public Works Department

 

Phone Number:                     (310) 253-5627

 

Fiscal Impact:                     Yes [X]     No [  ]                     General Fund:                     Yes [  ]     No [X]

 

Attachments:                     Yes [  ]     No [X]

 

Public Notification:                     E-Mail: Meetings and Agendas - City Council (06/##/2026)

 

Dept Approval:                      Yanni Demitri, Public Works Director/City Engineer (04/22/2026)

_____________________________________________________________________

 

 

RECOMMENDATION

 

Staff recommends the City Council (1) approve revised final plans and specifications for Phase 1 of the Better Overland Project, CIP No. PS029,; (2) award a construction contract to Toro Enterprises, Inc. as the lowest responsive and responsible bidder in the amount of $1,253,149 for Phase 1 of the Better Overland Project,; and (3) authorize the Public Works Director/City Engineer to approve change orders to the contract in an amount not-to-exceed $288,163.03 (23%) to cover contingency costs.

 

 

BACKGROUND

 

The Better Overland Project is an active transportation improvement project along Overland Avenue, beginning at Venice Boulevard and extending southward to the Fox Hills neighborhood, including the Culver City Transit Center at the Westfield Culver City.

 

Planned improvements include:

 

 

•                     More than 2.5 miles of protected bike lanes

•                     A new signalized crosswalk at the Julian Dixon Library

•                     New sidewalks, sidewalk repairs, and ADA improvements

•                     Sidewalk-facing streetlighting

•                     New traffic signals at Overland Avenue & Kelmore Avenue/Ranch Road and Overland Avenue & Sawtelle Boulevard

 

The City Council approved the conceptual plans for the Better Overland Project at their May 28, 2024, meeting. The plans were developed after extensive community outreach and engagement conducted earlier in 2024.

 

Staff is currently working to implement Phase 1 of the Project. The limits of Phase 1 are improvements along Overland Avenue between Venice Boulevard (City limit) and Culver Boulevard. Phase 1 also includes a new signalized pedestrian crosswalk at the Julian Dixon Library.

 

 

DISCUSSION

 

Revised Plans & Specifications

 

The City Council approved the final plans and specifications for Phase 1 at their January 26, 2026, meeting. At that meeting, the Council also directed staff to revise the design to use concrete median barriers to protect the new bike lanes included in the Project in lieu of flexible posts, where feasible. The plans have been updated accordingly.

 

Staff has also made the following revisions in response to recent community feedback received in 2026:

 

•                     Retain a southbound right-turn lane at Overland Avenue and Washington Boulevard

•                     Retain a southbound right-turn lane at Overland Avenue and Culver Boulevard

•                     Addition of a new accessible parking space

 

To maintain an all-ages-and-abilities bicycle facility, a protected bike lane will be installed to the left of the right-turn lane, reducing conflicts with turning vehicles. A short mixing zone is required in advance of the turn lane to allow vehicles to enter the lane. This zone will be clearly delineated with green pavement markings, and the bike lane alignment has been refined to ensure that cyclists are in a high-visibility, priority position. Staff believes the revised design maintains a high level of comfort consistent with the Project’s intent.

 

To accommodate these changes, previously proposed painted curb extensions at these intersections have been removed. To improve pedestrian visibility and increase yielding compliance, staff will implement Leading Pedestrian Intervals (LPIs) at both intersections. LPIs provide pedestrians with a WALK indication before adjacent vehicles receive a green signal, allowing pedestrians to enter the crosswalk and establish visibility and priority over turning traffic.

 

Finally, there are currently no accessible parking spaces on this portion of Overland Avenue. Phase 1 of the Project will construct 1 new accessible parking space on the corridor to promote accessibility for people with disabilities. This new space will be denoted by appropriate signage and markings and be located near a ramp to minimize distance from a parked vehicle to the sidewalk.

 

 

Award of Construction Contract

 

The City Council authorized staff to post a Notice Inviting Bids (NIB) for construction of Phase 1 at their January 26, 2026, meeting. The NIB was posted on PlanetBids on February 12, 2026. On April 2, 2026, the City’s Purchasing Division opened the bids. One bid was received from Toro Enterprises, Inc. in the amount of $1,253,149.

 

Staff reviewed the bid and determined it to be responsive and complete. Toro Enterprises, Inc. has successfully completed several projects for the City, including the Robertson Boulevard Complete Street Project and the MOVE Culver City Downtown Corridor Eastern Segment Project.

 

Construction is scheduled to begin in Summer 2026. Due to long lead times for signal equipment, the signalized crosswalk at the Julian Dixon Library is anticipated to be completed in late 2026/early 2027. All other improvements are expected to be substantially complete by Fall 2027.

 

 

ENVIRONMEMTAL REVIEW

 

On May 28, 2024 the City Council adopted a resolution finding that the project is categorically and statutorily exempt from the California Environmental Quality Act (, or CEQA).

 

 

FISCAL ANALYSIS

 

Inclusive of contingencies, the total project construction cost is estimated to be $1,541,312.03. Funding is available in  the following accounts:

 

Fund

Org

Object

Project

Description

Mobility DIF

43780000

730100

PS029

Better Overland

Capital Grants

42380000

730100

PS029

Better Overland

Mobility DIF

43780000

730100

PF025

Bike Ped. Action Plan

CCPFA

49980000

730100

PFA05

Streets & Right Away Improv.

 

 

 

 

 

CIP Projects PS029 (Better Overland), PF025 (Bicycle-Ped. Action Plan Implement), XXXX (Street and Right of Way Improvements), and Public Works Department operating accounts to support construction of the Project.

 

ENVIRONMEMTAL REVIEW

 

On May 28, 2024 the City Council adopted a resolution finding that the project is categorically and statutorily exempt from the California Environmental Quality Act, or CEQA.

 

ATTACHMENTS

 

The revised Phase 1 plans can be viewed at the Project’s webpage at

<http://www.culvercity.gov/betteroverland>

 

 

recommended action

MOTION

 

That the City Council:                     

 

1.                     Approve revised final plans and specifications for Phase 1 of the Better Overland Project, CIP No. PS029; and

 

2.                     Award a construction contract to Toro Enterprises, Inc. as the lowest responsive and responsible bidder in the amount of $1,253,149 for Phase 1 of the Better Overland Project; and

 

3.                     Authorize the Public Works Director/City Engineer to approve change orders to the contract in an amount not-to-exceed $288,163.03 (23%) to cover contingency costs.;

 

4.                     Authorize the City Attorney to review/prepare the necessary documents; and

 

5.                     Authorize the City Manager to execute such documents on behalf of the City.