CC - Award of a Contract to Peterson-Chase General Engineering Construction, Inc. as the Lowest Responsive and Responsible Bidder for the Construction of the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938 in an Amount Not-to-Exceed $77,440 ($70,440 Base Contract Plus $7,000 in Contingency Authority).

📥
Save a copy for yourself
Click ↓ Download to save this record and its files to your device, so you can read it later or share it with someone else.
File Number
15-190
Type
Minute Order
Status
Consent Agenda
Final Action
CC - Award of a Contract to Peterson-Chase General Engineering Construction, Inc. as the Lowest Responsive and Responsible Bidder for the Construction of the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938 in an Amount Not-to-Exceed $77,440 ($70,440 Base Contract Plus $7,000 in Contingency Authority).
On Agenda
8/24/2015
In Control
City Council Meeting Agenda

Full Text

title

CC - Award of a Contract to Peterson-Chase General Engineering Construction, Inc. as the Lowest Responsive and Responsible Bidder for the Construction of the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938 in an Amount Not-to-Exceed $77,440 ($70,440 Base Contract Plus $7,000 in Contingency Authority).

 

body

Contact Person/Dept: Hon Wang / Public Works

Phone Number:  (310) 253-5604

 

Fiscal Impact:  Yes [X]    No []                                                                 General Fund:  Yes [X]     No []

 

Public Hearing:  []                               Action Item:                     []                     Attachments:   Yes []     No [X]   

 

Commission Action Required:     Yes []     No [X]    Date:

Commission Name:          

 

Public Notification:   (E-Mail) Meetings and Agendas - City Council (08/19/15)  

 

Department Approval:                       Charles D. Herbertson

Public Works Director/City Engineer (08/14/15)

______________________________________________________________________

 

 

RECOMMENDATION

 

Staff recommends the City Council award a construction contract to Peterson-Chase General Engineering Construction, Inc. (Peterson-Chase), as the lowest responsive and responsible bidder, for the construction of the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938 in an amount not-to-exceed $77,440 ($70,440 Base Contract Plus $7,000 in Contingency Authority).

 

 

BACKGROUND

 

The Duquesne Avenue Bridge over Ballona Creek was originally constructed in 1937. The expansion joint steel plates and welds at the bridge deck have shown significant deflection under normal vehicular traffic and generate vibration and noise.  Included in the City Council Adopted Budget for Fiscal Year 2015/2016, this project will replace the two aging expansion joints with stiffer steel plates. This is the second time this project has been advertised for construction bids.  Each time only one bid was received.  This time there were four companies that obtained bid documents but only one submitted a bid. The lack of bidders is most likely due to the specialized nature of this work which can only be performed by a relatively small number of contractors.    

 

DISCUSSION

 

The Notice of Inviting Bids was published in the local newspaper, industry trade journals and posted on the City’s website.  On July 23, 2015, the City Clerk’s Office publicly opened the bid. Only one contractor responded with the following bid amount:

 

Contractor                                                                                                         Total Bid Amount

 

Peterson-Chase, Irvine, CA                                          $70,440

 

Staff reviewed the bid proposal of the lowest bidder, Peterson-Chase, and found the bid documents responsive and complete.  Its bid bond, contractor’s license, and worker’s compensation insurance were reviewed and determined to meet City requirements.  Peterson-Chase is a reputable contractor in the industry and has completed numerous similar bridge repairs for Caltrans.

 

Staff recommends that the City Council authorize the Public Works Director/City Engineer to approve change orders in an amount not-to-exceed $7,000 (10%) if necessary for unforeseen conditions.

 

Project management will be performed by the City‘s Engineering Division.  Construction inspection will be conducted by a contract deputy inspector for welding work.

 

The proposed bridge repair will require the temporary closure of the Duquesne Avenue bridge on 2~3 weekends, during which time the traffic will be detoured. Changeable message signs will be placed one week in advance of the bridge closure.

 

 

FISCAL ANALYSIS

 

Estimated Project Expenses

 

Construction Amount: Duquesne Avenue                     $70,440

(Bridge Expansion Joint Repair Project)

Construction Contingency                                                                                     $  7,000

Total Estimated Project Expenses                                          $77,440

 

Available Funding

 

Citywide Bridge Repairs - PZ938, Fund #420                     $79,525

Total Available Project Funds                                                               $79,525

 

 

ATTACHMENTS

 

None

RECOMMENDED MOTIONS

 

That the City Council:

 

1)                     Award a construction contract to Peterson-Chase General Engineering Construction, Inc. as the lowest responsive and responsible bidder for the Duquesne Avenue Bridge Expansion Joint Repair Project, PZ-938 , in an amount not-to-exceed $77,440 ($70,440 Base Contract plus $7,000 in contingency authority); and,

 

2)                     Authorize the Public Works Director/City Engineer to approve change orders in an amount not-to-exceed $7,000, if necessary; and,

 

3)                     Authorize the City Attorney to review/prepare the necessary documents; and,

 

4)                     Authorize the City Manager to execute such documents on behalf of the City.

 